How to protect your margin on fixed-fee work

See how extra hours affect your fixed-fee margin. Estimate the cost of finishing and use recorded work to discuss scope changes with your client.

For agencies and consultants delivering projects for an agreed price.

Updated

Check what the project has cost so far, then estimate what it will take to finish. Compare that total with the fee you agreed.

Review extra scope and rework with your client while you can still change the plan. Recording more hours does not automatically increase a fixed fee.

Update your forecast while you can act

Expected margin = (agreed fee − expected total delivery cost) ÷ agreed fee × 100. Use a positive fee and exclude tax from both sides.

  1. Start with the agreed scope

    Check what the fee includes and how many review rounds you allowed. Keep extra requests separate until you agree how to handle them.

  2. Add costs so far

    Count recorded project time at internal cost rates, then add expenses. Include rework even if you will not bill it separately.

  3. Estimate the cost to finish

    List the remaining tasks and who will do them. Update the estimate when the work changes, not only when the budget runs out.

  4. Choose the next action

    Compare the total expected cost with the fee. Discuss a scope change, revised delivery plan or additional fee while there is still time.

Example: an extra review round

A fictional agency has an $8,000 USD fee. This delivery forecast excludes overheads and tax.

Example: an extra review round
Forecast Cost Amount left from the fee
Original finish estimate $5,000 $3,000 remaining: 37.5% margin.
Extra review round $1,000 more $2,000 remaining if the fee stays unchanged.
Revised finish estimate $6,000 total $2,000 remaining: 25% margin.

The extra work reduces the expected margin by 12.5 percentage points. Agree any additional charge with your client before treating it as part of the fee.