Free project time estimate worksheet

Put hours behind your next quote. Break the work into tasks, allow for uncertain steps and keep your scope notes beside the estimate.

Editable XLSX for Excel or Google Sheets · no signup or email

Download worksheet (XLSX)

Use the worksheet in three steps

  1. 1. Name each task

    Replace the example with up to 15 pieces of work. Add the deliverable or assumption beside each one.

  2. 2. Compare three hour estimates

    Enter optimistic, most likely and pessimistic hours. Keep them in that order, including any expected revision time.

  3. 3. Check the quote notes

    Review the total, currency and included work. Edit the exclusions and assumptions before sending your own quote.

Example

A small website refresh

A fictional designer estimates discovery, a design draft, one client review and handover. The design draft assumes the client supplies existing brand assets.

Discovery

1 / 2 / 3 hours → 2.00 weighted hours

Design draft

4 / 6 / 10 hours → 6.33 weighted hours

Client review

2 / 3 / 5 hours → 3.17 weighted hours

Handover

1 / 2 / 3 hours → 2.00 weighted hours

Total: 13.50 weighted hours. At USD 120 per hour, indicative labour is USD 1,620 before other costs or tax.

The example includes one consolidated review round. Extra rounds, hosting and copywriting are excluded until separately agreed.

What the estimate means

For each task, weighted hours = (optimistic + 4 × most likely + pessimistic) ÷ 6. The workbook adds unrounded task results and rounds the total to two decimals. This three-point method is described in PMI's scheduling standard.

Hours describe effort, not a promised finish date. Parallel work, waiting for feedback and calendar availability need separate planning. The worksheet is an estimate, not accounting, tax or legal advice.

A named task with missing, negative or out-of-order hour inputs shows “Check inputs” and blocks the total. Empty rows do not count. The rate is optional for estimating hours, but the indicative labour amount needs a non-negative rate. Use one ISO currency code throughout and confirm other costs and tax separately.

The download includes a fictional example and amber cells to edit. Your project and client details stay in the file you save or upload to your chosen spreadsheet service; this page does not ask for them.

Questions before you quote

Is the weighted estimate a guaranteed hour total?

No. It gives one planning figure from your three assumptions. Keep the range and client dependencies visible when agreeing scope.

Can I use this for a fixed fee?

Yes, as an internal starting point. Add other costs and your pricing judgement before setting a fixed fee. State what is included in your actual quote.

Can I edit it in Google Sheets?

Yes. Upload the XLSX to Google Sheets. Check the imported formulas and print layout before sharing your edited copy.

Compare your estimate with real hours.

Track client work in TimeLodge, then review the hours before you invoice. See time tracking or see pricing.

Start free

Free for 14 days — every feature, no credit card, no automatic charge.

Start free, record your next project hour, then compare it with your estimate before invoicing.